We anticipate that West Genesee Street will be paved (top course) between Weatheridge Drive to Knowell Road (Friendlys) on Tuesday and Wednesday of next week. Final striping of the road will also be done in this section.
We tentatively anticipate that the top course paving on West Genesee Street between Knowell and Hinsdale on Saturday, October 5th. The lanes closures would not occur until after 8 AM to accommodate students getting to school for SATs. I will provide another update with these details when we finalize paving dates for this section.
As for updates on the traffic signal work, while all work is not complete on the signals, certain elements have been recently installed that will allow the signals to operate more efficiently. Between Kasson and Hinsdale Road, this work should be done today and Monday that will result in less delay than what is being seen currently. Please note that the signals still will not be 100% efficient, but they should be more responsive. Again, once we finish the top course (we have more wireless detectors to be installed directly in the top course) and finish the needed electronics, we fully intend to program our new timings, but this will not be completed for several weeks.